Leak test of stainless steel reactor

Date:2021-06-16Source:Views:

Water filling leak test procedure of stainless steel reactor


① Before water filling test, all accessories and other components welded with stainless steel reactor body shall be completed.


② Before water filling test, all welds related to tightness test shall not be painted.


③ Fresh water shall be used for water filling test, and the water temperature shall not be lower than 5 ℃. For stainless steel reactor, the chloride ion content in water shall not exceed 25mg / L, and the water for aluminum floating roof test shall not have corrosive effect on aluminum.


④ 0.1-0.2mpa compressed air shall be injected into the reinforcing ring before water filling test for weld leakage detection.


⑤ In the water filling test, the observation of foundation settlement should be strengthened. In the water filling test, if the foundation settlement is not allowed, the water filling should be stopped and the test can be continued after treatment.


⑥ During the process of water filling and discharging, the breathing valve port shall be opened, and the foundation shall not be soaked. The water filling height shall be the highest operating liquid level. When the strength of stainless steel storage reactor is tested, the liquid level shall be maintained for 48h, and the stainless steel reactor wall shall be observed to be qualified without leakage and abnormal deformation. If any leakage is found, water shall be drained. Before draining, mark and make the liquid level about 300 mm lower than the leakage point, and then carry out repair welding.


⑦ During the strength and tightness test of the stainless steel reactor top, the water level in the stainless steel reactor should be LM below the maximum liquid level, and the pressure should be increased slowly. When it is increased to the test pressure (1.1 times of the designed internal pressure), it is qualified to observe that there is no abnormal deformation in the top pouring and no leakage in the weld (soapy water). The stability test of the stainless steel reactor top should be filled with water to the designed maximum liquid level, The water discharge method is used. During the test, the pressure should be lowered slowly. When the test negative pressure is reached, the stainless steel reactor top is qualified if there is no abnormal deformation. After the above two tests, the stainless steel reactor should be connected with the atmosphere immediately, and return to normal pressure. In the weather that causes drastic temperature changes, it is not suitable to do the strength, tightness and stability test of the fixed top.


Wuxi Municipal sea Petrochemical Equipment Co., Ltd. is a professional manufacturer of chemical and pharmaceutical equipment. The company has strong technical force, complete equipment, advanced production technology, perfect detection means, reliable quality and superior performance.


A professional factory that manufactures chemical and pharmaceutical equipment, a comprehensive enterprise integrating R&D, production and service

Technical Support:YOUWEI

Tel:+86-13606176623

Add:East of yuanhu road, wutang community, Xue lang street,Binhu District, Wuxi City, Jiangsu Province (inside gongming machinery)

Email:cnrq@cnrq.com

主站蜘蛛池模板: 97色伦午夜国产亚洲精品| 国产午夜亚洲精品不卡下载| 无码免费午夜福利片在线| 国产成人精品一区二区在线小狼| 欧洲精品一卡2卡三卡4卡影视| 少妇人妻无码永久免费视频| 国产精品成人无码久久久久久| 国产精品99久久久久久宅男小说| 人妻中文无码久热丝袜| 亚洲成在人线a免费77777| 日韩一级一区二区不| 99久久超碰中文字幕伊人| 亚洲aⅴ在线无码播放毛片一线天| 朝鲜女人大白屁股ass孕交| 亚洲国产综合精品2020| 精品高潮呻吟99av无码视频| 亚洲妓女综合网99| 亚洲人成色77777在线观看| 久久受www免费人成看片| 色偷偷色噜噜狠狠网站年轻人| 国产久操视频| 人妖与黑人做爰| 久久久久se色偷偷亚洲精品av| 国产精品国产对白熟妇| 亚洲日本中文字幕天天更新| 无码专区一ⅴa亚洲v天堂| 亚洲中文字幕日本无线码| 亚洲国产手机资源在线| 性中国videossexo另类| 尤物yw午夜国产精品视频| 欧美性白人极品1819hd| 久久久久久国产精品无码下载| 亚洲日韩国产一区二区三区在线| 亚洲国产综合精品2020| 国模雨珍浓密毛大尺度150p| 国产亚洲日韩a欧美在线人成 | 久久国产av影片| 久久久久久人妻一区二区三区| 国产小呦泬泬99精品| 久久精品黄aa片一区二区三区| 长腿校花无力呻吟娇喘的视频|